Contents
List the definitions and acronyms used in this document in alphabetical order
Acronym / Item |
Expansion / Definition |
SVT |
Smart Vision Trial |
The purpose of this document is to summarize the end to end testing activities performed by QA team as part of release 2.6 for Smart Vision Trial.
End to end functional and regression testing of Smart Vision Trial is completed.
Period of Testing: 15th December 2021 to 14th February 2022
N/A
Innovation Engineering - Smart Vision Trial - All Documents (sharepoint.com)
N/A
Module |
Limitations |
Smart Vision Trial (SVT) |
|
Smart Vision Trial (SVT) |
# of User Stories |
# of Test Cases |
# of Open Defects (Critical/High/Med/Low) |
||||||
Total |
Fully |
Partially |
Total |
Passed % |
Critical |
High |
Medium |
Low |
|
Release 2.6 |
53 |
51 |
2 |
118 |
95.00% |
0 |
0 |
10 |
2 |