List the definitions and acronyms used in this document in alphabetical order
Acronym / Item |
Expansion / Definition |
Platform |
SmartOps Core Platform |
The purpose of this document is to summarize the end to end testing activities performed by Smartops QA in platform as part of Release 7.5.
End to end functional testing (for 7.5.0 ,7.5.1 and 7.5.2) is completed.
Period of Testing: 7th Jul 2021 to 30th Aug 2021
Jira ID |
Test Status |
Comments |
59025 |
Verified – QA Passed |
|
TFS ID |
Test Status |
Comments |
|
|
|
NA
Area |
Description |
Clones |
Destination configuration queue not working |
Clones |
Distorted icons /profile section on page refresh |
PWF |
Dependency field is not implemented for smartops component – Rule Engine |
PWF |
Deleting deactivated projects are disabled for now |
PWF |
Page refresh is needed when user edit/removed dependency fields |
SmartOps Platform |
# of User Stories |
# of Test Cases |
# of Open Defects |
||||||
(Critical/High/Med/Low) |
|||||||||
Total |
Fully |
Partially |
Total |
Passed % |
Critical |
High |
Medium |
Low |
|
Passed |
Passed |
||||||||
Release 7.5 |
64 |
64 |
0 |
713 |
98% |
0 |
0 |
9 |
3 |
Release 7.5 Regression |
Regression is planned in parallel with Stage testing |