Contents
List the definitions and acronyms used in this document in alphabetical order
Acronym / Item |
Expansion / Definition |
PWF |
Packaged WorkFlow |
The purpose of this document is to summarize the end to end testing activities performed by QA team as part of AIOps Release 2.6.0
End to end functional and regression testing of AIOps is completed.
Period of Testing: 13th May 2022 to 8th June 2022
|
AIOps |
||
Delivery -TFS ID |
AIOps – TFS ID |
|
Comments |
7732 |
91810 |
Verified – QA Passed |
|
8170 |
96750 |
Verified – QA Passed |
|
8654 |
97962 |
Verified – QA Passed |
|
N/A
Module |
Limitations(Deferred Defects) |
AIOps PWF |
|
AIOps PWF |
# of User Stories |
# of Test Cases |
# of Open Defects (Critical/High/Med/Low) |
||||||
Total |
Fully |
Partially |
Total |
Passed % |
Critical |
High |
Medium |
Low |
|
Release 2.6.0 |
28 |
26 |
2 |
174 |
90% |
0 |
0 |
7 |
0 |
Manual Regression - 2.6.0 |
|
|
|
113 |
99% |